Lakes Restoration Project

Survey Tally, Summer 2003

Thank you very much for your responses. As of Wednesday (7/30/2003), 205 surveys have been returned. Considering the short time frame for return and the vacation season, this is a very good response rate. Your valuable input and ideas are being incorporated into a plan to complete the restoration project.

The survey results indicate that the Loch Alpine community would like to complete the Lower Lake restoration quickly, with work on further improvements to follow completion of the Lower Lake. The table shows the priority scale averages for remaining project components on the survey. They have been arranged as indicated by averaging the community’s responses. (Updated: based on 215 responses.)

 

#1

Rating

#2 Rating

#3 Rating

#4 Rating

Total Score

Mean

Priority Ranking

Huron River Silt Clean-up

212

2

 

1

220

1.02

1

Disposal Site Survey

212

1

1

1

221

1.03

2

Consultant/

Engineering

212

1

1

1

221

1.03

2

Lower lake silt removal

168

33

4

11

289

1.34

3

Boyden Creek Retention Pond

93

66

33

24

416

1.93

4

Landscaping

37

66

70

41

543

2.52

5

Fish Replacement

44

56

67

48

549

2.55

6

Upper Lake

Pathway

36

62

54

63

574

2.66

7

Lower Lake Pathway

35

50

57

73

598

2.78

8

Fishing Dock

16

38

71

89

661

3.07

9

Paved Parking

17

34

61

103

680

3.16

10

Boat Racks

11

28

65

109

701

3.26

11

Survey Priority Scale

  1. Critical, important to complete quickly
  2. Important, complete if funds allow
  3. Marginal, would like to see completed but could be postponed
  4. Not interested in seeing completed