Board Journal
Final Road Sealing
Posted on Oct 3rd, 2023

Final Seal Coating this Week
Our contractor will complete the last seal coating this week on two streets. Look for signs posted on the roads the evening before the scheduled sealing. Work may begin as early as 7:00 am and roads may remain closed as late as 6:00 pm on the following:
  • East Loch Alpine Drive
  • Sylvan Drive
Slurry top coat requires 3-4 hours minimal cure time. No traffic or parking will be permitted on these roads until the slurry has cured. If you live on these roads and need to use your car during the slurry sealing, we suggest that you park on one of the adjacent streets.
 
Work schedule is dependent on weather. This sealing cannot be done if it rains. If there are questions, please feel free to contact Brian McCall by email at mccallbrian@msn.com or by phone at (734) 426-4546.