LASA Water Main Replacement Update 9/21
Posted on Sep 21st, 2017
LASA Water Main Replacement Project Update: Finishing work to commence soon.
There is a work list of many lots that will be attended to beginning soon by the contractor for grass seeding/soil as needed, culvert cleaning and uncovering some few valve boxes. The final work of restoration at affected properties will begin soon, probably in the next 10 days. If anyone is concerned about something at their lot, related to the water main replacement project, contact:
Ted Erickson, Project Manager
(734) 657-4925
terickson@processresults.com
Bob Sendra. LAIA Board Director
(734) 426-2427
robertsendra4746@comcast.net